If you furnish labor or materials on a construction project in Kings County, a preliminary notice is what protects your right to get paid. The rules are set by California state law — the same across every county — but where you ultimately record a mechanics lien is local to Kings County. Here’s what subcontractors and suppliers in the county need to know.

What is a preliminary notice?

A preliminary noticeis a written notice that preserves your right to record a mechanics lien if you aren’t paid. California requires almost every subcontractor, supplier, and equipment lessor to serve one (Cal. Civ. Code §§ 8200–8216). Without it, you generally can’t enforce a lien — even for a valid debt.

The 20-day deadline applies in Kings County

You must serve the notice within 20 days of first furnishing labor or materials to the project (Cal. Civ. Code § 8204). Serve it late and it only protects work from the 20 days before service. Use the preliminary notice deadline calculator to find your exact date.

Who you serve

Serve the owner or reputed owner, the direct (general) contractor, and the construction lender if there is one (Cal. Civ. Code § 8200). The accepted methods are certified or registered mail with return receipt, or personal delivery — see how to serve a preliminary notice.

Construction in Kings County

Kings County construction leans institutional and agricultural. Naval Air Station Lemoore and three state prisons make federal and state agencies recurring project owners, while dairy and row-crop operations drive freestall barns, digesters, and processing plants. The recorder requires an APN on the face of every real-property document.

Preliminary notice and mechanics lien rules apply to private projects throughout the county, including Hanford, Lemoore, Corcoran, Avenal, Armona, and Kettleman City. To confirm an owner or parcel before you serve, the Kings County Assessor is a useful starting point.

Recording a mechanics lien in Kings County

If you go on to record a mechanics lien, it must be recorded at the Kings County Clerk-Recorder — the office that records liens and deeds for property in the county. A lien always gets recorded in the county where the property sits, so a Kings County project means recording with the Kings County recorder.

Your lien deadline is 90 days from completion, or as little as 30 days for subcontractors (60 for the direct contractor) if a Notice of Completion is recorded (Cal. Civ. Code §§ 8412, 8414). See the mechanics lien deadline guide for the full timeline.

Frequently asked questions

Related guides

Serve your Kings County preliminary notice in minutes

Notice Harbor prepares and mails your California preliminary notice by Certified Mail, verifies recipient addresses, and tracks your deadlines. Your first notice is free.

Start your free notice

This page is general information, not legal advice, and does not create an attorney–client relationship. California lien and notice deadlines are strict and fact-specific — “completion” alone can be triggered by actual completion, the owner’s occupancy or use, or a 60-day cessation of labor. Notice Harbor is not a law firm. Confirm any deadline that matters to your claim with a licensed California construction attorney.