If you furnish labor or materials on a construction project in Tehama County, a preliminary notice is what protects your right to get paid. The rules are set by California state law — the same across every county — but where you ultimately record a mechanics lien is local to Tehama County. Here’s what subcontractors and suppliers in the county need to know.
What is a preliminary notice?
A preliminary noticeis a written notice that preserves your right to record a mechanics lien if you aren’t paid. California requires almost every subcontractor, supplier, and equipment lessor to serve one (Cal. Civ. Code §§ 8200–8216). Without it, you generally can’t enforce a lien — even for a valid debt.
The 20-day deadline applies in Tehama County
You must serve the notice within 20 days of first furnishing labor or materials to the project (Cal. Civ. Code § 8204). Serve it late and it only protects work from the 20 days before service. Use the preliminary notice deadline calculator to find your exact date.
Who you serve
Serve the owner or reputed owner, the direct (general) contractor, and the construction lender if there is one (Cal. Civ. Code § 8200). The accepted methods are certified or registered mail with return receipt, or personal delivery — see how to serve a preliminary notice.
Construction in Tehama County
Tehama County construction is dispersed and rural — ag structures, ranch improvements, and well and septic work across large holdings, rather than urban density. Corning is a national olive-processing center, Interstate 5 supports distribution development through Red Bluff, and the 2024 Park Fire added substantial rebuild and hardening work in the high-severity zones.
Preliminary notice and mechanics lien rules apply to private projects throughout the county, including Red Bluff, Corning, Los Molinos, Gerber, Tehama, and Manton. To confirm an owner or parcel before you serve, the Tehama County Assessor is a useful starting point.
Recording a mechanics lien in Tehama County
If you go on to record a mechanics lien, it must be recorded at the Tehama County Clerk and Recorder — the office that records liens and deeds for property in the county. A lien always gets recorded in the county where the property sits, so a Tehama County project means recording with the Tehama County recorder.
Your lien deadline is 90 days from completion, or as little as 30 days for subcontractors (60 for the direct contractor) if a Notice of Completion is recorded (Cal. Civ. Code §§ 8412, 8414). See the mechanics lien deadline guide for the full timeline.
Frequently asked questions
Related guides
Serve your Tehama County preliminary notice in minutes
Notice Harbor prepares and mails your California preliminary notice by Certified Mail, verifies recipient addresses, and tracks your deadlines. Your first notice is free.
Start your free noticeThis page is general information, not legal advice, and does not create an attorney–client relationship. California lien and notice deadlines are strict and fact-specific — “completion” alone can be triggered by actual completion, the owner’s occupancy or use, or a 60-day cessation of labor. Notice Harbor is not a law firm. Confirm any deadline that matters to your claim with a licensed California construction attorney.